The As-Samra WWTP BOT Project Construction view:
The project includes the design, construction, procurement, commissioning, operation, maintenance and financing of the new wastewater treatment plant (WWTP), Phase 1, at As Samra. The WWTP is to be built on the site of the existing stabilization ponds, to be taken over by the Project Company and potentially used in the project. The plant shall have a capacity of 267 000 m3/day.
The project also includes expansion and upgrading the pre-treatment plant at Ain Ghazal, the minor refurbishment of the pumping station at West Zarqa, as well as operation and maintenance of the main conveyor lines from the pre-treatment facilities at Ain Ghazal to the WWTP and of the pumping stations at Hashimiyya and West Zarqa.
The construction of As Samra WWTP is divided into two stages. In the current project-stage 1, the capacity for the design year 2015 is to be achieved. In stage 2, an expansion for a capacity the year 2025 is planned. While it is a requirement in stage 1 to design the layout of the plant to facilitate for an expansion in stage 2, such expansion is not part of this project.
Financing:
The project total construction price is JD120,2 million, (financed through a syndication of Jordan financing institutions lead by the Arab Bank) and the Project Sponsors. Where USAID contributed $ 78Million as grant to the project through MWI, MWI contribution is $14 Million, with the reminder being invested by the project company in the form of equities and debt financing from the lenders.
MWI Contribution/USAID grant
Although the RFP specified that the successful Bidder should secure all financing for the Project, MWI undertook to provide a fixed contribution of 50% of the costs of the Project up to US$ 75 million. This undertaking was based on an agreement between USAID and the MWI whereby USAID agreed to fund this contribution, subject to the following conditions:
Availability of the agreed fund from USAID; (commitment letter was obtained before the effectiveness of the project)
USAID would not enter into any agreement with the Project Company;
MWI shall raise the wastewater tariff by 12% as recommended by previous studies in order to support the financial requirements of the Project during the operational phase and as part of the securities that would make the project financiable and attractive to the private sector;
Funding from USAID would be based on the Fixed Amount Reimbursement (FAR) method. Under such method of payment the total amount that USAID will pay for a particular Section is fixed in advance (according to special appendix to the Project Agreement);
A majority of the shares of the Project Company must be held by firms with U.S. nationality with the balance of shares held by firms with a Code 935 Country,
The EPC Contractor must have U.S. nationality, and any subcontractor providing services for the EPC Contractor must have a Code 935 Country as its nationality;
The O&M Contractor must have a Code 935 Country as its nationality
All commodities for the Works must have their source and origin in a Code 935 Country
The Project Company shall use commodities whose source and origin are either United States of America or Jordan in the execution of the Works (“US/Jordan Commodities”) with a value corresponding to at least fifty (50) per cent of the total actual cost of commodities for the Works.
The involvement of USAID in the As-Samra Project created a number of significant benefits:
The funding from USAID, as a grant paid throughout the construction period, reduced the amount of private financing required for the Project including the level of equity to be provided by the Sponsors;
The funding from USAID resulted in reducing the Treatment Charges payable by MWI. TC were substantially reduced by (65%), and as a result the Project became attractive, financiable and affordable;
USAID Payment Conditions:
Payments from USAID to the Project Company will be made during the construction period subject to the following conditions (the Payment Conditions):
• That Completion Certificates are issued by MWI with respect to an operational section of the plant (a Section), with confirmation that:
• The Nationality Requirements are satisfied;
• That the Commodities Requirements are satisfied in accordance with the Compliance Plan;
• That the Project Company is not in breach under the Project Agreement or under the Facility Agreement and that none of the Sponsors is in breach of its equity and continuing shareholding obligations; and
• That USAID has made a positive USAID Determination with respect to the relevant portion of the MWI Contribution if required.
FAR Method and Completion of Sections
Under the FAR method of payment the total amount that USAID will pay for a particular Section is fixed in advance in an amount specified in an appendix to the Project Agreement.
According to the RFP, each Bidder shall fill the appendix (MWI contribution) by designing and structuring the work to be completed in Sections that are brought into service in successive stages. Filling the MWI contribution appendix requires bidders to identify the relevant anticipated cost of each Section to be covered by MWI. This allowed the contractor to receive the MWI contribution for the first completed sections which allows deferring the draw of money under the facility agreement (debt financing) as well as structuring the equity injection and consequently reduction in interest rates during the construction period.
Environmental Concerns prior to the new plant
ENVIRONMENTAL CONDITIONS
The effluent from As-Samra WSP plant does not meet Jordanian effluent standards and is not suited for reuse in agriculture due to poor biological quality and high nitrogen content. Its oxygen demand on the receiving stream is excessive, and its high nutrient content stimulates undesirable aquatic plant growth.
Complaints of odor emissions from AinGhazal Treatment Plant (AGTP), and As-Samra WSP, are frequent. At AGTP improved odor control facilities are planned to control and treat odors from the septage discharge facilities and from the septic wastewater entering the siphon. At As-Samra WSP, the inlet facilities have been covered and odor scrubbers have been installed. The continued use of anaerobic ponds will continue to cause odor problems.
As-Samra WSP effectively removes nematode eggs, but it requires disinfection by chlorination to control fecal coliforms. Operation of the chlorination process is intermittent. Therefore, bacterial quality is unreliable. Effluent used for irrigation along the banks of Wadi Dhuliel and the Zarqa River does not consistently meet bacterial quality standards. Therefore, consumption of the food crops produced there carries some risk of disease transmission, and direct contact with the receiving stream water should also be avoided. However, the removal of nematode eggs does eliminate an important threat to public health.
The discharge from King Tala Reservoir (KTR) has declined in quality to the point where it is not suitable for unrestricted irrigation based on Total Dissolved Solids (TDS), nitrogen, and fecal coliforms.
Groundwater in the As-Samra area has declined in quality since the As-Samra WSP began operation. However, there is insufficient data to indicate that seepage from the ponds is the reason. In fact, it is suspected that local irrigation with treatment plant effluent from the wadi, livestock operations, and over fertilization have been major contributors to the groundwater quality decline. The rise in groundwater levels attributed to seepage from the ponds may be more the result of the cessation of well operations in favor of surface water.
Public Health
An epidemic of waterborne cholera occurred in the Zarqa basin about 1985 which was attributed to discharges from AGTP. Whether the cause of the epidemic was attributed to treated effluent or to combined raw sewage/storm water bypass is not clear. The utilization of the WSP at a site more remote from the urbanized area was influenced by this event. Concern remains that such an episode could recur.
Water Quality for Agriculture
Reclaimed water suitable for irrigation of most crops can be achieved by providing secondary treatment such as Waste Stabilization Ponds. Secondary treatment can reduce Biological Oxygen Demand (BOD5) and Total Suspended Solid(TSS) loadings to acceptable levels, but will have little, if any, affects upon TDS, nitrogen, phosphorous, boron or chloride. Expensive tertiary treatment and/or source control would be required to reduce these elements.
The effluent from the existing WSP meets requirements for irrigation of crops when chlorination is practiced to control coliforms and for crops less sensitive to salinity. There may be additional yield reductions in some crops due to high levels of chloride and nitrogen.
Short-term improvement of 1995
In 1995 A short improvements program was commissioned under the assistance of USAID for investment cost $ 11 million. The As-Samra Wastewater Stabilization Ponds Emergency Short-Term Improvement Program is one of an Improvement Program for the rehabilitation and expansion of the Amman wastewater system. This contract included:
- The removal of sludge from four anaerobic ponds
- Construction of two anaerobic ponds, to replace the deconstructed
- Construction of new inlet structure to accommodate with water flow in peak time
- Construction of inter-pond pipelines and attendant structures
- Construction of odor control facilities, chlorination facilities and installation of surface aerators in two ponds at the inlet.
Improvement considered only one third of the plant at that time, awaiting the long term solution.